Wind Park Kreuzstetten
In Windpark Kreuzstetten 13 wind turbines of the type Vestas V90 - 2 MW with an installed capacity of 26 MW produce over 60 million kWh of clean electricity from wind power. This corresponds to an average supply of 18,000 households.
The electricity is fed into the public network at the transformer station in Bisamberg. For this purpose, underground cables have been laid from Kreuzstetten to the transformer station. The CO² saving amounts to over 48,000 tons per year.
| Specifications |
| Location: | 2123 Hautzendorf |
| YOC: | 2005 - 2008 |
| Power Plants: | 13 installations |
| Type: | V 90 / 2 MW |
| Output: | 26 MW |
| Annual Output: | 69,3 Mio kWh |
| Eco-Audit |
| Energy for: | 19.750 households |
| CO² savings: | 48.309 t |